Welcome to the SR 72 Improvements Project (from McCoy Road to SR 71) website. This project will reconstruct deteriorating pavement, widen SR 72 to increase traffic capacity and operations, add pedestrian, bicycle and transit facilities, and improve safety. Improvements will begin in Summer 2022 and are expected to be complete by Summer 2024.

Delaware Route SR 72 and Delaware Route 71 Intersection Construction

Location:Delaware Route 72 and Delaware Route 71 Intersection
Dates and Times:Tuesday, September 5, 2023, at 12:00 am through Monday, September 12, 2023, at 5 am, pending weather

As part of the ongoing Phase 1 construction work, the contractor will close the northerly Delaware Route 71 leg of the Delaware Route 72 and Delaware Route 71 intersection for approximately 4-5 days to complete pavement work.

The following movements at the intersection will not be permitted during this period: 

    • Delaware Route 71 Southbound right, thru, and left turns
    • Delaware Route 71 Northbound thru
    • Delaware Route 72 Southbound left turns
    • Delaware Route 72 Northbound right turns

Once construction of the northerly Delaware Route 71 leg is complete, the contractor will pave the center of the intersection and the center of Delaware Route 72 across the Red Lion Hundred shopping center entrance for approximately 2-3 days.

Center of SR 72 Pavement Reconstruction 

Location:East of American Boulevard/Connell Drive intersection to Fieldstone Crossing Drive
Dates and Times:Monday, June 12, 2023, until Friday, June 23, 2023, pending weather
As part of the ongoing Phase 1, Stage 1 construction work, the center pavement of SR 72 will be reconstructed from about 500’ east of American Boulevard/Connell Drive intersection to just west of Fieldstone Crossing Drive. Northbound SR 72 traffic will be shifted onto the newly constructed pavement. The work will be completed in 3 – 350’ long sections. Left turn movements will be restricted in work areas under construction.

SB SR 72 Pavement Overlay

Location:N/A
Dates and Times:Week of October 3rd through Monday Morning October 10th
Nighttime pavement patching operations will occur Monday through Thursday throughout the week of October 3rd. Beginning Friday night, October 7th at 8PM, through Saturday morning, October 8th at 6AM, SR 72 will be reduced to a single lane under a flagging operation from the train tracks north of Willamette Drive to the SR 72 and SR 71 intersection to install an asphalt overlay. Expect delays. Beginning Saturday morning, October 8th at 6AM, through Saturday evening, October 8th, southbound SR 72 will be closed from the intersection of SR 71 to south of Wilson Blvd. For those travelling on southbound SR 72, the following detour route will be utilized:
    • The detour route will instruct drivers on southbound SR 72 to turn left onto northbound SR 71, continue northbound on SR 71 and turn right onto Church Rd. Continue south on Church Rd and turn right at the stop sign onto southbound SR 7, continue southbound on SR 7 to access destinations along SR 72.
All movements will be maintained from Wilson Boulevard leg and the Wilbur School elementary school entrance leg. View Detour Map During the detour, access to private driveways and businesses will be maintained. During the detour, access to southbound SR 72 from the businesses at the Red Lion Hundred will be detoured to Old Kirkwood Road and to northbound SR 71 along the signed detour route. Southbound SR 72 will be reopened to motorists and SR 72 will be shifted into the Phase 1 traffic pattern by Monday morning at 5 am.