Welcome to the SR 72 Improvements Project (from McCoy Road to SR 71) website. This project will reconstruct deteriorating pavement, widen SR 72 to increase traffic capacity and operations, add pedestrian, bicycle and transit facilities, and improve safety. Improvements will begin in Summer 2022 and are expected to be complete by Summer 2024.
Delaware Route SR 72 and Delaware Route 71 Intersection Construction
Location: | Delaware Route 72 and Delaware Route 71 Intersection |
Dates and Times: | Tuesday, September 5, 2023, at 12:00 am through Monday, September 12, 2023, at 5 am, pending weather |
As part of the ongoing Phase 1 construction work, the contractor will close the northerly Delaware Route 71 leg of the Delaware Route 72 and Delaware Route 71 intersection for approximately 4-5 days to complete pavement work.
The following movements at the intersection will not be permitted during this period:
-
- Delaware Route 71 Southbound right, thru, and left turns
-
- Delaware Route 71 Northbound thru
-
- Delaware Route 72 Southbound left turns
-
- Delaware Route 72 Northbound right turns
Once construction of the northerly Delaware Route 71 leg is complete, the contractor will pave the center of the intersection and the center of Delaware Route 72 across the Red Lion Hundred shopping center entrance for approximately 2-3 days.
Center of SR 72 Pavement Reconstruction
Location: | East of American Boulevard/Connell Drive intersection to Fieldstone Crossing Drive |
Dates and Times: | Monday, June 12, 2023, until Friday, June 23, 2023, pending weather |
SB SR 72 Pavement Overlay
Location: | N/A |
Dates and Times: | Week of October 3rd through Monday Morning October 10th |
-
- The detour route will instruct drivers on southbound SR 72 to turn left onto northbound SR 71, continue northbound on SR 71 and turn right onto Church Rd. Continue south on Church Rd and turn right at the stop sign onto southbound SR 7, continue southbound on SR 7 to access destinations along SR 72.