Delaware Route SR 72 and Delaware Route 71 Intersection Construction

As part of the ongoing Phase 1 construction work, the contractor will close the northerly Delaware Route 71 leg of the Delaware Route 72 and Delaware Route 71 intersection for approximately 4-5 days to complete pavement work.

The following movements at the intersection will not be permitted during this period: 

    • Delaware Route 71 Southbound right, thru, and left turns
    • Delaware Route 71 Northbound thru
    • Delaware Route 72 Southbound left turns
    • Delaware Route 72 Northbound right turns

Once construction of the northerly Delaware Route 71 leg is complete, the contractor will pave the center of the intersection and the center of Delaware Route 72 across the Red Lion Hundred shopping center entrance for approximately 2-3 days.